This website has been archived and is no longer updated.

The content featured is no longer current and is being made available to the general public for research and historical information purposes only.


Powerhouse Museum - Home


Back


 
Lifting devices
Snowy - MAIN

The location of the Snowy power stations, relative to engineering services available in the capital cities, was remote indeed. Thus the SMAwas obliged to be self sufficient in almost all areas of engineering. With heavy plant and equipment being manufactured overseas, items were broken down into more manageable loads, both in weight and rail track clearance dimensions (to allow for tunnels and bridges through which items passed).

As an example, even a transformer for Tumut 1 Power Station weighing 81.2 tonnes, would be unloaded at the rail head and transported by road to the site and unloaded. Overhead travelling cranes were set up at the rail head at Cooma, Cudgewa, and Tumut to unload onto the Authority's ANTAR road transporter vehicles.

ANTAR
ANTAR refers to the name of a Persian poet who was, apparently, renowned for his Herculean feats of strength. The vehicle was made in England. Its first major deployment was in the Middle East during the early 1950s, primarily to transport oil pipes. It was named ANTAR so that it would be recognised by the Persian workers. In the SMA's version it was redesigned to have the capability of hauling 121.9tonne loads (162.6 tonne tare weight of vehicle) from Cooma into Tumut 1 PowerStation, and climb up the steep mountain again fully loaded with a 121.9 tonneload, which the road train achieved (using two prime movers, pull-push) while consuming fuel at the rate of 4.3 km per 10 litres of diesel fuel.
truck

Cranes
A variety of large cranes, shovel loaders, and flying foxes were used on dam and power station construction sites. Two overhead cranes, which could be operated independently or coupled in tandem, were installed in the power station to move the transformers into place. The cranes were designed to accommodate the maximum weight of the equipment to be installed. In the case of Tumut 1, each assembled generator rotor is in excess of 203 tonnes. The rotor was delivered in component pieces and assembled on site.

Lifting beams
In order to handle such a weight, a lifting beam was constructed. The beam is held between each of the two crane hooks while the rotor is supported by a central split ring, which fits in a recess in the shaft, and secures the self-aligning attachment to the beam. This allowed the heavy load to be lifted and very accurately lowered into the generator stator.

Special equipment
Throughout all power stations there are special facilities for lifting power plant items such as turbine runners, pumps, compressors, air receivers, and the like. Items can be lifted, pulled or pushed and positioned accurately without undue manual effort. In some cases, special equipment is required such as when fitting a long 330kv insulated porcelain bushing into a transformer located outdoors. When such an item is inclined to the vertical, the degree of handling difficulty is increased, but innovative lifting gear has overcome such problems.

Erecting towers
At the Upper Tumut Switching Station, the 330kv switchyard consists of many lattice towers, beams and supporting structures. When constructed, there were no mobile cranes as we see available today. The whole of the switchyard steelwork was erected using: pulleys, block and tackle, steel wire ropes and winches on motor vehicles.

to lift components high above the ground and to erect the towers. Looking at the switchyard today, 40 years on, one would find it difficult to imagine that expert rigging practices and not cranes, were used to erect the steelwork.

Multiple hydraulic jack system
Main transformers are large capacity items up to 101 tonnes each. These have to be unloaded on arrival using the power station overhead crane to remove the load from the road transporter, fitted out and then re-positioned on wheels in the transformer bay. An innovative piece of equipment used was a 508 tonnes German manufactured MFD multiple hydraulic jack system. This enabled the complete transformer to be jacked up and the direction of the wheels changed to allow it to move into the transformer bay. Such equipment is also used to right overturned locomotives or train carriages, which have been derailed.

These few examples indicate the degree of self reliance necessary to construct major engineering work in remote mountain areas where lifting devices are not readily available from commercial sources. After the construction period was finished (1974), further innovation has taken place, including the use of air bags to lift and transport loads.

HSC technology syllabses support - HOME spacer Snowy! Power of a nation